Project 06
Remote / lakefront build.
Operational record. Remote build executed under access, staging, and weather/logistics constraints.
Context
Remote site conditions required front-loaded planning: access, staging, storage, and sequencing decisions made before mobilization.
Scope
- Site logistics plan (deliveries, laydown, storage, protection).
- Build sequence structured to minimize remobilization and wasted trips.
- Closeout packaging aligned to remote turnover realities.
Constraints
- Access limitations (roads, ferries, seasonal conditions) and delivery scheduling.
- Material storage and protection on site; theft/weather considerations.
- Trade availability and scheduling compression due to travel time.
Duration
Sequenced to lock critical path early (structure → envelope → rough-ins → interior). Remobilization was treated as a cost/schedule risk and minimized.
Mid-build changes
- Weather-driven resequencing — documented and executed to protect work-in-place.
- Client selection change — treated as a controlled change with procurement impacts logged.
Final outcome
Project closed with stable performance and documented handover despite remote constraints; system checks and deficiencies resolved prior to final turnover.